TPS150-DR1S12A: a 150 W, 12 V DIN rail power supply for industrial projects that need a clear electrical, thermal, and procurement decision. This adjustable AC/DC supply provides 12–15 VDC output, a 12.5 A rated current, and a documented 170% power boost for 10 seconds. For system integrators and panel builders, its value depends on how those ratings match the actual load and enclosure.
TPS Elektronik GmbH can support this product class with product selection, equivalent solutions, and project consultation for global B2B customers. Use this guide to qualify the TPS150-DR1S12A product reference, then discuss your application through the TPS DIN rail solutions page. The objective is a technically useful RFQ that connects engineering requirements with a workable purchasing specification.
Qualify the exact 12 V model. The pictured TPS150-DR1S12A has front-access terminals, a DC OK indicator, and voltage adjustment. Confirm the production version and controlled documentation in your RFQ.
Key specifications and application fit
The TPS150-DR1S12A belongs to the TPS100–320W Peak DR+ family. Its ordering reference in the supplied datasheet is 901004401; the shop identifies it as DR1016. Include both references when requesting a quotation to avoid confusion with the 24 V version or another power class.
The family datasheet identifies automation, LED lighting, and telecommunications as application areas. This 12 V model is a candidate for compatible controllers, communication devices, lighting assemblies, and auxiliary electronics. These are application examples, not blanket approvals for every connected device. First confirm operating voltage, startup demand, and the environment of each load.
| Parameter | Datasheet value | Decision relevance |
|---|---|---|
| Input | 85–264 VAC, 47–63 Hz; or 120–370 VDC | Confirm the actual supply range and DC-input installation conditions. |
| Output | 12–15 VDC adjustable; 12.5 A; 150 W | Check voltage, continuous current, and power together. |
| Temporary boost | 170% for 10 seconds; automatic recovery | Validate peak duration, repetition, and voltage behavior. |
| Efficiency | 92% at 220 VAC and maximum load | Use the model value, not the family maximum of 93%. |
| Hold-up / ripple | 20 ms at full load and 230 VAC; ripple/noise <1% of output voltage | Compare with device reset and disturbance limits. |
| Power factor / leakage | >0.96; <0.5 mA at 264 VAC, 50/60 Hz | Include in mains and leakage-current assessment. |
| Environment | 0–70°C with derating from 50°C; 5–95% RH, non-condensing; altitude 3000 m | Specify cabinet ambient and confirm altitude conditions. |
| Storage | −25°C to 85°C | Define transport and storage requirements. |
Three selection gates before a purchase decision
Electrical fit: the continuous demand must remain inside both the current and power limits at the intended voltage. Adjustable output does not mean constant maximum current across the entire adjustment range. Confirm the permissible operating envelope with TPS if using a setpoint above 12 V.
Environmental fit: assess the local ambient around the energized supply, not just room temperature. The installation needs vertical rail mounting, a clear convection path, and a power budget corrected for temperature. Humidity and altitude also belong in the project specification.
Commercial fit: procurement should establish the exact article, document package, quantity, delivery date, and destination. A technically suitable component still needs a confirmed supply arrangement. TPS can discuss the target model or assess an equivalent solution against the same acceptance requirements.
For a genuinely 24 V architecture, compare the 150 W TPS150-DR1S24A selection guide. A voltage-adjustable 12 V model does not cover a 24 V bus. Keeping the voltage family explicit prevents avoidable BOM and commissioning errors.
Check installation space early. The rear gallery view shows the rail attachment and ventilation openings. Allow service access and verified clearances beyond the body dimensions.
Size the 12 V bus and validate the 170% boost
Start with a load table covering normal operation, startup, and future expansion. List current at the intended supply voltage, simultaneity, undervoltage limits, and cable length. Add a project-defined reserve for changes; there is no universal reserve percentage that suits every enclosure or duty cycle.
Continuous current and voltage adjustment
At 12 V, 12.5 A corresponds to 150 W. A 9 A load uses 108 W, leaving 42 W before temperature derating and any additional reserve. At 15 V, the same 9 A requires 135 W. Conversely, 12.5 A at 15 V would require 187.5 W, beyond the stated 150 W continuous rating. These calculations are selection checks, not a manufacturer-issued current-versus-voltage curve.
Raising the output can compensate for some cable drop only when every connected load accepts the higher voltage. Verify voltage at both the nearest and farthest devices under minimum and maximum demand. Do not compensate for undersized wiring by exceeding a load’s approved input range.
What the ten-second boost means
The datasheet specifies 170% output power for 10 seconds with automatic recovery. Applied to 150 W, that percentage gives a calculated 255 W screening value. At 12 V, the corresponding arithmetic current is 21.25 A. Neither figure establishes a guaranteed transient operating point under every line, temperature, or repetition condition.
Give TPS the actual peak amplitude, duration, spacing between events, and acceptable voltage dip. A measured motor-start or capacitive-charge waveform is more useful than a general statement that the load has “high inrush.” Confirm recovery behavior and whether the proposed cycle allows sufficient thermal recovery.
Branch protection also matters. A supply may remain active while a distant device resets because of wiring drop, or protection may operate before the load starts. Evaluate the complete power path, including connectors, fuses, electronic protection, and the load’s undervoltage threshold.
For frequent or sustained overload, compare a higher continuous rating within the TPS Peak DR+ power-boost range. Temporary capacity should not carry a continuously undersized design. Review the 12 V model’s ordering details and use TPS application-selection support to confirm the load profile before releasing the BOM.
Setpoint and startup belong in one load review. Confirm the chosen voltage, continuous demand, and transient profile together; the 10-second boost is a temporary operating feature.
DIN rail installation, wiring, and thermal limits
The mechanical drawing for the 100–150 W units shows a 43 mm width, 127 mm height, and 76.5 mm body depth. Treat these as body dimensions: allow additional space for rail hardware, terminal access, cable bends, and the manufacturer’s installation clearances. Confirm the current drawing before freezing the panel layout.
Mount vertically on TS 35/7.5 or TS 35/15 rail. Convection cooling avoids reliance on an internal cooling fan, but it still requires an unobstructed air path. Nearby drives, relays, transformers, and tightly routed cables can raise the local temperature or restrict circulation.
Read the full temperature derating curve
The supplied covered-unit curve indicates 100% output through 50°C, approximately 70% at 60°C, and approximately 10% at 70°C. For a 150 W unit, these graphical points correspond to about 105 W and 15 W respectively. They are preliminary readings from the family curve; confirm the model-specific limits and test conditions with TPS.
The earlier 108 W example already exceeds the approximate 105 W available at 60°C, even before reserve. This is why a 0–70°C operating range cannot be read as 150 W available at every temperature. Consider a larger rating, improved ventilation, or another suitable architecture when the cabinet runs hot.
At the documented 92% efficiency and 150 W output, estimated conversion loss is 150 × (1/0.92 − 1), or about 13 W. The efficiency figure applies at 220 VAC and maximum load. Use this estimate for initial heat budgeting, then validate the actual enclosure at the intended line, load, and ambient conditions.
Terminals, monitoring, and safe commissioning
The datasheet lists AWG 26–14, or 0.15–2.5 mm², for input and DC terminals. This connection range does not make every accepted conductor suitable for 12.5 A. Select cable by current, length, temperature, grouping, voltage drop, and applicable installation rules. Request tightening torque and termination instructions.
The 100–150 W terminal diagram identifies PE, N, L, DC minus, DC plus, and a power-fail contact: closed means AC OK; open means AC fail. Confirm contact voltage/current ratings and isolation before connecting a controller. Repeated DC terminals are connection points; do not assume separately regulated or independently protected outputs.
During panel acceptance, verify polarity, protective earth, setpoint, loaded voltage at the devices, startup behavior, temperature, and alarm response. Request confirmation of upstream protection and DC-input wiring instructions where relevant. Installation and testing should be performed by appropriately qualified personnel.
Cabinet temperature controls usable output. Preserve the convection path and evaluate the local ambient. The datasheet curve substantially reduces available power above 50°C.
Qualification evidence, reliability, and supplier evaluation
The supplied datasheet lists overtemperature, overvoltage, and overload protection, a five-year warranty, and demonstrated MTBF above 350,000 hours at full load and 25°C ambient. Protection names alone do not specify thresholds, trip delays, short-circuit mode, or restart timing. Request those details when failure behavior affects machine availability.
MTBF is a statistical reliability measure under stated conditions, not an expected operating life or a promise of uninterrupted service. Compare it with temperature exposure, switching duty, maintenance access, spare-unit strategy, and the consequences of a stopped process. Ask TPS to confirm the applicable warranty terms for the quotation.
Check the controlled compliance package
The datasheet references the Low Voltage Directive 2014/35/EU, EMC Directive 2014/30/EU, UL 508, UL 60950-1, and EN 60950-1. It also uses UL, CE, and TÜV wording in the family features. These references are document statements; they do not independently establish the current certificate scope for your exact article and destination.
The shop gallery includes a declaration image dated June 18, 2017. Treat it as historical document context and request the current controlled declaration and any applicable certificates. Verify model coverage, standard editions, issuing body, and installation conditions. A component’s documentation does not by itself approve the completed panel or machine.
The immunity entry cites IEC 801 parts 2–6, Level 3. Do not automatically equate that wording with your project’s present EMC test specification. Provide the equipment environment, cable arrangement, required emissions and immunity criteria, and target markets so TPS can review the available evidence.
Choose alternatives by requirements
If continuous demand is lower, investigate the TPS GP DIN rail family for smaller loads. Confirm the selected variant’s actual voltage, current, thermal, and document requirements; family membership alone is not equivalence. For test development, a programmable source may be a separate tool rather than the installed panel supply.
TPS can support product selection and discuss equivalent products, cabinet integration, engineering consultation, or project-specific customization. Define the requested scope: modified wiring or a configured assembly is different from changing the certified power supply itself. Availability, engineering feasibility, test scope, and commercial terms need confirmation in the proposal.
For company owners and product managers, a useful supplier comparison combines purchase cost with qualification effort, cabinet space, heat management, serviceability, and delivery risk. Procurement should request a written technical response against the same requirement list from each candidate supplier.
Historical document image, dated June 18, 2017. This gallery image is shown for context. Request the current controlled declaration and applicable certificate package for the exact model and target market; it is not proof of present project compliance.
Prepare a qualified TPS150-DR1S12A RFQ
A focused inquiry helps TPS answer with the appropriate product, documentation, and commercial scope. You do not need to finish the entire design before contacting sales; identify the confirmed requirements and mark the remaining decisions.
- Product and quantity: TPS150-DR1S12A, DR1016 / 901004401; prototype quantity, first order, and estimated annual demand.
- Electrical conditions: AC or DC input range, desired output setpoint, continuous current, peak waveform, event repetition, and required ride-through.
- Installation: maximum internal ambient, enclosure and ventilation, rail space, altitude, wiring lengths, and alarm-contact use.
- Qualification: destination countries, required current declarations/certificates, equipment-level test requirements, and acceptance criteria.
- Delivery: requested date, delivery address and postal code, forecast, labeling or packing needs, and integration support.
Request confirmed price, availability, lead time, shipping terms, and document deliverables for the specified quantity. Discuss alternatives if the requested model cannot satisfy the technical or delivery conditions. Do not base a project commitment on an unconfirmed stock indication or general family description.
Move from component comparison to an application-specific proposal. Send TPS your load profile, enclosure temperature, compliance requirements, quantity, and schedule. TPS can assess this 12 V DIN rail power supply and discuss suitable alternatives or integration support for your B2B project.
View the TPS150-DR1S12A target product · Discuss DIN rail selection and request a quotation
Frequently asked questions
What are the rated output and efficiency?
The model is rated 150 W and 12.5 A with 12–15 VDC adjustment. Its stated efficiency is 92% at 220 VAC and maximum load. The family headline of up to 93% is not this model’s individual rating.
Can it provide 12.5 A continuously at 15 V?
Do not assume so: that operating point would require 187.5 W. Confirm the allowable current at your chosen setpoint and temperature with TPS before design release.
Can the 170% power boost replace a larger supply?
Only after the actual transient has been validated. The specified boost lasts 10 seconds; sustained demand and repeated starts require separate electrical and thermal assessment.
Is full output available at 70°C?
No. The supplied curve falls from full output at 50°C to about 70% at 60°C and 10% at 70°C. Ask TPS to confirm the applicable model-specific curve.
What should I send TPS for an equivalent or integrated solution?
Provide voltage, continuous and peak demand, cabinet conditions, required documents, quantity, and schedule. Use the TPS DIN rail product and solution channel to start the review; customization scope and delivery commitments are confirmed in the proposal.